Web Version: F. Estimated Costs
Back

F. Estimated Costs

In order to estimate the construction costs for the entire project, projected dates were established by I&S with guidance from the building committee. I&S then assigned construction costs based on historical data and added inflationary factors to project the costs to the time that actual construction might occur on a given phase. The following chart indicates the potential phases for each component and their associated costs. As a projected date could change, so too would the associated costs. Soft costs, such as architecture and engineering, specialized consulting, testing, and legal fees are not indicated and will add between 10% to 15% of the construction costs.

Your Project(s)

Date Projected

Square Feet

Cost / SF

2005 Construction Cost

Inflationary Factor

Projected Total Cost

1. Sanctinasium

2008

15,000

$125.00

$1,875,000

1.03

$1,950,000.00

2. Sanctinasium Lower Level

2008

15,000

$65.00

$975,000

1.03

$1,000,000.00

3. Site Improvements 1

2008

$800,000

1.03

$825,000.00

4. Alton Avenue and Backage Road

2008

$500,000

1.03

$525,000.00

5. Detention Ponds

2008

$100,000

1.03

$125,000.00

6. Plaza

2011

22,350

$10.00

$223,500

1.09

$250,000.00

7. Cemetery

2011

$100,000

1.15

$125,000.00

8. Permanent Sanctuary

2014

27,150

$150.00

$4,072,500

1.15

$4,700,000.00

9. Outdoor Amphitheater & Recreational Areas

2014

$500,000

1.15

$575,000.00

10. Connecting Spaces

2014

5,470

$125.00

$683,750

1.15

$800,000.00

11. Covered Walkway

2014

2,500

$40.00

$100,000

1.15

$125,000.00

12. Trail System

2014

$100,000

1.15

$125,000.00

13. Classrooms & Administrative Space

TBD

15,000

$125.00

$1,875,000

1.09

$2,000,000.00

14. Classroom/Admin. Lower Level

TBD

15,000

$65.00

$975,000

1.09

$1,100,000.00

15. Sanctuary Additions

TBD

12,000

$150.00

$1,800,000

1.15

$2,100,000.00

16. Administrative Additions

TBD

12,000

$125.00

$1,500,000

1.15

$1,775,000.00

17. Narthex Addition

TBD

2,425

$150.00

$363,750

1.15

$425,000.00

 

 

   
Total Construction Costs $18,527,000.00